FEEDER 308

Phase: Complete

Biennial Plan: 1st

Location: Ward 3

Neighborhoods: Friendship Heights American University Park, Tenleytown, Chevy Chase 

Biennial plan - a detailed proposal that identifies a group of overhead electrical distribution feeders that the DC PLUG initiative would like to underground over a two year period.

Timeline

  • June 14, 2019 - Groundbreaking Ceremony 

  • April 30, 2020 - Civil Construction Complete

  • January 13, 2021 - Construction Complete 

  • December 2021 - Electrical Completion

Feeder 308 News

DC PLUG Announces the Completion of Feeder 308 – July 30, 2021
The DC PLUG team announces the completion of Feeder 308 in Ward 3. Resiliency and reliability improved by 95% against major storm related outages for about 595 customers. The team is proud to report that 100% Certified Business Enterprises (CBEs) were used for the civil and electrical work. Click the video below to review the announcement.

Watch the video here.